Dear All,
I am facing issue of “infeasible solution” on OSeMOSYS MUIO version 5.3 for my country level energy transition model. The main issue is days in day type, as my time slices are 12 months, with no weekdays or any other division, despite several attempts by redoing the model, i am still facing the same issue of time slice which shows in the model platform, but when i run the model it does not account for it in the solver log as it should be, which lead to infeasible solution, any idea or suggestion what could be the possible solution in this case?
If your model does not include day types, the value for the parameter DaysInDayType should default to 1. If that is already the case, the unfeasibility issue is likely originating from another part of the model.
Thank you so much for the reply, i can also share all the model files whith you, can you have a look and suggest me, what might be the possible reason behind the infeasible solution, i tried many things within the model, but still it shows infeasible.
Regards,
Watan Yar
I sincerely appreciate the opportunity to share my work with you. I have been attempting to upload the OSeMOSYS Pakistan model; however, the process has unfortunately been unsuccessful due to technical limitations. I would be grateful if you could kindly provide me with an alternative means, such as an email address, to which I may directly send the compressed (zip) file.
Thank you very much for your time and consideration.
Dear Fernando,
Thank you so much for replying. I saw your video on MUIO and it really helped me clear the confusion. The model is now running, if possible, can you take a look at results and approach, once i finish in next two weeks?
I’m still going through a busy period. Please let me know if you have any specific doubts regarding your results or approach. Unfortunately, I don’t have time for a full review of your study at the moment.